Skills
Education
- Banha University - Cairo -EgyptSept 2004 / July2009 : Electrical power and machines
Grade / GPA : 66.68%
Qualification : Bachelor's degree
Experience
- Thyssenkrupp Industrial SolutionsJune-2022 / Present : Electrical Field Engineer
Yearly Salary : 48000$
Job Duties :Project NCIC Phase 2 ( Ammonia - Urea - Ammonium nitrate ) plants Responsibilities: • Supervise the construction teams assist to resolve engineering and coordination on site • liaise between the construction teams and system accomplishment and vendor packages for commissioning and startups • Inspect the work done and generate punch list for the installations works • Assure all punch items are cleared before next construction stage to start • follow up on construction plans make sure systems completed and ready for commissioning • witness all motor loop checks and solo run tests • attend final walk through for Mechanical completion for all electrical systems • Assist in commissioning and equipment energizations - CSI Energy Group (Tanzania )Sept 2016 - Dec 2021 : Electrical Construction Manager
Yearly Salary : 48000
Job Duties :Position: Tender Assistance Company: CSI Energy Group Project East Africa Crude Oil Pipeline Responsibilities: • Set up execution plan for the main line block valves shelters fit out scope of work • Create a detailed bill of quantities for the scope of work and identify scope of supplies • Analyze technical specification for required materials, equipment • Considered in the execution plan and materials procurement • Identify required resources and equipment make sure all are included in the pricing schedule • Identify the work breakdown and sequence of work for project schedule proposal Period May 2019 - June 2021 Position Construction Manager Company CSI Energy Group Project Maternity and Newborn Hospital (MH) CCBRT Tanzania Responsibilities: Manage scope of work for supply and installations for HVAC and ICT with total Value $6.5M include installation of: HVAC Chilled water-cooling system (chillers – Air handling units -FCU -piping – ducting) VRF cooling system (Indoors – outdoors – piping) ICT Data and voice – CCTV -Access control – Fire alarm – Nurse call • Identify required resources (manpower – material- tools –equipment) for project construction • Review Project schedule, work breakdown, and sequence of activities before submission • Review contract specifications make sure materials and equipment supplies comply and deviation • Identified • Review RFA, RFI for technical submittals for supplied materials and equipment • Approve purchase requests and orders, issuance PO, follow up till materials arrive to site • Review and sign off interim payment applications submitted to main contractor • Preview and approve payment applications submitted by subcontractors • Project reporting progress – commercials – financial • Site inspection and preparing reports internal and external reports for managing the site, checking plans, drawings & quantities for accuracy of calculations, ensuring That all materials used and work performed are as per specifications. • Monitor work schedule and create 3 weeks’ forecast • Plan testing and commissioning activities and follow up on project handover Period Sept 2016- May 2019 Position Construction Manager ( Electrical ) Company CSI Energy Group Project Julius Nyrere International Airport Terminal 3 Client BAM International ( Tanzania Airport Authority ) Responsibilities: • Manage scope of design supply and install of all electrical, fire alarm and public address of total $10.5 M include - 22/KV / 6.6 /0.4 KV sub stations and backup generators - UPS system and battery chargers - Small power and lighting systems - Fire alarm and public address systems • Set up project resources planning for the installations scope or work for manpower and resources • Setup project organization chart and detailed responsibility matrix for whole project team member • Follow up on engineering schedule and drawings submission for approval • Set-up project budget and cash flow study for installations scope • Initiate procurement process by raising purchase requests, review issuance PO, and payment process • Create subcontract packages for the whole scope of work • Review project monthly report before submission to client • Review project financial report budget follows up, cash flow, profit / loss assessment • Implementing compliance of company with ISO auditing certification • Responsible for site inspection and preparing reports and documentation of site inspection. • Planning the work and efficiently organizing the plant and site facilities in order to meet deadlines. • Managing the site, checking plans, drawings & quantities for accuracy of calculations, ensuring That all materials used and work performed are as per specifications • Follow up on testing and commissioning plan activities for the electrical system - Hanwha S&C (Tanzania)Aug2014 - Aug2016 : Electrical Construction Manager
Yearly Salary : $32000
Job Duties :Project Muhimbili University for Health and Allied Science. Tanzania Client Kolon Global Corporations Responsibilities: • Preparation of Project Planning, scheduling and Monthly Progress Reports. • Responsible for site inspection and preparing reports and documentation of site inspection. • Planning and efficiently organizing the plant and site facilities in order to meet agreed deadlines. • Handling cable tray & trucking installation, cable pulling, termination and, testing • Managing the site, checking plans, drawings & quantities for accuracy of calculations, ensuring • Materials used a n d work performed are as per specifications. • Manage and Control Manpower, Material Plan and Budget • Arrange Electrical Working Schedule • Coordination between Construction Teams • Supervise and Monitor subcontractor’s installations activities • Monitoring and inspection for: Installations of Lighting (Normal –Emergency-UPS), fire Alarm, public address CCTV , ICT , Nurse callers system • Electrical installations in Special systems room (Operation rooms – MRI – CT scan – X-rays ) • Testing MCC and Startup - Doosan Heavey IndustriesMarch 2012 / February 2014 : Lead Electrical Site Engineer
Yearly Salary : 16000$
Job Duties :Project El Ain El Sukhna Thermal Power Plant (2x650 MW) CP105 Client East Delta Power Electrical Production Co. Responsibilities: • Lead, direct and monitor the site activities • Cable tray and supports installations for Boiler Building • Design and fabrication of cable tray's Supports • Coordinate between Scaffolding, Tray installation groups and workshop • Lighting fixture & power Sockets installations • Junction Boxes and IC- Rack Installations • Power & Instrument Conduit installations • Junction boxes and Hook up installations • Installation for Electrical Panels (Lighting - BMS- MCC-Power transformers) • Supervise Workshop due to supports fabrications • Grounding and lightening installations • Installations of CCTV & Hoists • Assistance for Commissioning and Testing Team - KahromikaOct 2009 : Electrical Site Engineer
Yearly Salary : March 2012
Job Duties :Period March 2011 – Jan 2012 Position Electrical site engineer Company Kahromika Misr Company for Electrical & Mechanical Projects Project El Shabab Power Plant (8x125MW) CP101 – (GE) Gas turbine Client East Delta Power Electrical Production Co. (Kharafi National) Responsibilities: • Installations of all electrical related works at site • Installation of Fire detectors and fire alarm devices • Installation of Emergency lighting • Cable pulling and termination for fire detector& alarm and lighting • Conduit, Cable tray fabrication and installation • Electrical Testing and Commissioning Period Oct.2009 – March 2011 Position Electrical site engineer Company Kahromika Misr Company for Electrical & Mechanical Projects Project Cairo West Thermal Power Plant (2x350MW) CP117 Client Cairo West Electrical Production Co. (Inetic Inergia) Responsibilities: • Installations of Cable Tray and Conduit in Turbine building • Installation of heat tracing system • Hydrogen plant (All Explosion Proof Conduit Material) Electrical installations • Installation of Electrical Control Panels (MCC – DCS-switch gear) panels • Cable Pulling & termination